Harvard releases new 10-year plan for Allston

The University previews a 10-year expansion plan for its Allston campus.

A draft of the nine proposed projects in the new IMP.

A draft of the nine proposed projects in the new IMP. | Image courtesy of the Boston Redevelopment Authority

The new outline does not include the Health and Life Sciences Center, slated for groundbreaking in 2014, nor the Barry’s Corner Housing/Retail Commons slated for groundbreaking in 2013 with plans to open the following year—both were approved under the previous IMP.

The new outline does not include the Health and Life Sciences Center, slated for groundbreaking in 2014, nor the Barry’s Corner Housing/Retail Commons slated for groundbreaking in 2013 with plans to open the following year—both were approved under the previous IMP. | Image courtesy of the Boston Redevelopment Authority

The ten year plan for Barry's Corner includes various spaces with active ground floor uses.

The ten year plan for Barry's Corner includes various spaces with active ground floor uses. | Image courtesy of the Boston Redevelopment Authority

After 18 months of planning and community discussions, the University unveiled a new 10-year Institutional Master Plan Notification Form (IMPNF) at the Harvard-Allston task force meeting on October 11, enumerating projects that administrators deemed to have a “major transformative” effect on Harvard’s expanding campus.

“Those of you who have been involved in the previous 2007 filing,” said Harris S. Band, Harvard’s director of physical planning, will “find that this is quite a bit different in terms of scope, geography, time frame, and really, in terms of practicality.”

University speakers outlined nine major projects that will fall under the new IMPNF, including an addition to Harvard Stadium, a brand-new basketball gymnasium that will be built between 2017 and 2022, a hotel/conference center, and various renovations to building on the Harvard Business School (HBS) campus.

“We have a nice high-school gymnasium,” said Jeremy L. Gibson, senior associate director of Harvard Athletics, who was on hand to discuss the new athletics facilities with the community. “But we’d really like to play in a college stadium.”

The nine projects falling under the new IMPNF include:

  • HBS’s Baker Hall (residence facility), slated for renovation sometime between 2014 and 2016, (78,000 square feet, six stories); 
  • HBS’s Kresge Hall (mainly executive-education dining, administrative offices, and classrooms), to be replaced sometime between 2014 and 2016—with plans and lead funding for the project unveiled in a news conference at HBS on Friday (90,000 square feet, four stories);
  • HBS’s Burden Hall (mainly academic classrooms and a new auditorium), to be replaced sometime between 2016 and 2018 (130,000 square feet, three stories);
  • a new HBS faculty and administrative office building, to be built sometime between 2018 and 2020 (110,000 square feet, four stories);
  • a Harvard Stadium addition, sometime between 2017 and 2022, that will house a press box, club seating, an athletics office, and athletic facilities;
  • a new basketball stadium, located south of Harvard Stadium  and the outdoor track, but set back from the intersection of North Harvard Street and Western Avenue (see map), to rise sometime between 2017 and 2022 (60,000 square feet dedicated to the stadium and 40,000 square feet for mixed use and offices, between four and nine stories);
  • a mixed-institutional-use project, located adjacent to the new basketball stadium along Western Avenue, scheduled for sometime between 2017 and 2022 (200,000 square feet, six to nine stories), mainly for administrative offices with retail on the ground floor (administrators are aiming for an “active” ground floor “full of people”);
  • a hotel and conference center, located east of Western Avenue and adjacent to the south side of the HBS campus, to be built sometime between 2017 and 2022, with the hotel aiming for 150 to 250 rooms and ample conference center space (250,000 plus square feet, six to nine stories); and
  • Soldiers Field Park Housing Renovation, a housing complex located adjacent to HBS, planned for sometime between 2017 and 2022 (423,000 square feet, three to nine stories high).

The new outline does not include the Health and Life Sciences Center (already approved under the previous IMP), slated for groundbreaking in 2014, nor the Barry’s Corner Housing/Retail Commons, slated for groundbreaking in 2013 with plans to open the following year, which is still in the permitting process. Harris Band stressed that the new projects would be complementary to the University’s aspirations for Barry’s Corner (at North Harvard Street and Western Avenue). “We will be working very hard in our planning to make sure the ground plan, pathways, and streets work to connect these projects effectively to Barry’s Corner so that it is an intuitive connection,” he said.

The University is expected to file the IMPNF formally with the City of Boston next week. The community then has 30 days to give feedback before Harvard resubmits the plan to the Boston Redevelopment Authority. After a 60-day comment period, the BRA and the Boston Zoning Commission will decide whether or not approve the final IMP.

“This is not a monolithic program of projects that are very similar to each other,” Band told the task-force members and others at the meeting. “This is a very diverse variety of projects in terms of use, including executive education, classrooms, faculty and administrative offices, a hotel and conference center, housing, retail, and other ground-floor uses and open space. That variety is very important because it combines to make for a very dynamic area.”

See draft plans from the proposed IMP presented at an October 1 task-force meeting.

You might also like

Boston Board Approves Harvard’s Enterprise Research Campus Framework

City planners adopt principles to guide future development of the commercial innovation district in Allston.

A New Landscape Emerges in Allston

The innovative greenery at Harvard’s Science and Engineering Complex

The Enterprise Research Campus in Allston Nears Completion

A hotel, restaurants, and other retail establishments are open or on the way.

Most popular

An animal’s journey from grief to love shows how much humans need each other, too.

Meet Harvard’s 2026 Student Commencement Speakers

Two undergraduates and a Ph.D. candidate will address the graduating class on May 28.

Ronny Chieng Tells Harvard to ‘Destroy AI’ as Graduates Cheer

The comedian and The Daily Show host gave the keynote address for Class Day 2026.

Explore More From Current Issue

Massachusetts Hall at Harvard Red brick building with a large clock on top, surrounded by green trees.

With a grade inflation vote and in the courts, the University argued that it’s taking steps to change.

A woman with long hair stands confidently with crossed arms next to a pickup truck.

In her memoir All That's Unseen, Emilee Hackney explores religion, friendship, and home.

An open book with a film strip emerging, trailing popcorn and a dancer silhouette.

Readers Respond to Our Adaptations Survey

We asked people to share their favorite art adaptations. Here’s what they said.