Harvard offers $50 million toward Allston transit

The University tries to advance transit near its Allston commercial-development zone.

Photograph for Wikimedia Commons

Harvard has increased its potential financial commitment from one-third to more than one-half—about $50 million—of the total cost of West Station, a proposed commuter-rail station in Allston. In a letter from Harvard executive vice president Katie Lapp to Massachusetts Department of Transportation (MassDOT) secretary Stephanie Pollack, the University also proposed paying up to $8 million to set up a temporary commuter-rail station in Allston before West Station is completed.

MassDOT had initially planned to finish West Station by 2025, but announced last month that it would be 2040 before the station opened, due to uncertainty both about the volume of travel the station will eventually attract, and about funding. Harvard had previously committed to pay a third of the station’s cost, or about $30 million to $35 million. Allston residents have urged the state to complete West Station sooner, and, last week, a letter from Massachusetts politicians urged Harvard to “follow the example that New Balance set at Boston Landing by covering almost the entire cost of the station construction.”  

West Station is central to Harvard’s plans in Allston and the development of a neighborhood south of the Massachusetts Turnpike’s Allston Interchange.  The University's additional pledged contributions to the station, Lapp wrote today, “will support both an early neighborhood transit service (that may serve as a bridge to full service) and the introduction of the regional, multi-modal West Station…These investments also represent Harvard’s deep commitment to the Commonwealth’s long-term economic growth, the University’s longstanding and constructive partnership with its neighbors, and the objectives we all share for the future of a connected and economically vibrant community in Allston-Brighton.”

Last month, Harvard publicly filed plans to build a non-academic commercial district in Allston near Harvard Business School and the planned new science and engineering complex. The document proposes the development of 14 acres of land south of Western Avenue for commercial, office, and residential space. That plot is part of a larger, 36-acre parcel of land that has sat empty since Harvard acquired it in 2000. Longer term, as MassDOT completes plans for the reconstruction of the nearby highway viaduct and intersection, the much larger “Allston Landing South” parcel will become available for the development of a new, multi-use neighborhood connected to local transportation networks and universities, including Harvard’s science and engineering and business campuses to the north and the Longwood medical area to the south. Transit availability will, of course, affect Harvard’s ability to develop, and the value of developing, its commercial enterprise zone. 

Lapp’s letter acknowledged that some of the uncertainty around West Station’s construction “relates to the future demand that will only become clear when the University’s development plans advance—while the I-90 interchange project will be largely under construction for the better part of the next decade.” She continued:

On the path to regional transportation improvements, the North Allston Community will have endured a significant period of disruption and inconveniences related to the construction of the new I-90 interchange and related infrastructure…It is the University’s hope that by providing funding for an interim West Station facility, serious consideration can be given to an additional option for early phase 1 service even as the specific timing of the full West Station remains under review. As we discussed, Harvard fully recognizes that the decision as to when service should be introduced at an interim or full multi-modal West Station, and at what levels, are determinations that would need to be made by the MassDOT…Harvard also hopes that as MassDOT considers taking advantage of the University’s financial commitment to an “early action” station, it will consider the years of construction inconveniences endured by the local community in furtherance of this regional project in addition to assessing ridership and finances.                     

Read more articles by Marina N. Bolotnikova

You might also like

Harvard Data Trained This AI Model

“Talkie” is a large language model trained on only pre-1931 public domain content from Harvard libraries.

Harvard Stem Cell Institute Names New Faculty Co-Director

Biology professor Lee Rubin is a leading expert on neurogenerative diseases.

George Washington’s Sash on Display at Peabody Museum Starting May 25

A famous American fashion statement helps bring Revolutionary history to life.

Most popular

Harvard Faculty Approve a Cap on A Grades

Reforms to reduce grade inflation will take effect in the fall of 2027.

Harvard Discloses Top Earners’ Compensation

The University files its annual report for tax-exempt organizations.

AI Outperforms Doctors in Emergency Room Tasks, New Harvard Study Shows

Researchers say the technology could help physicians with triage, diagnosis.

Explore More From Current Issue

Three joyful graduates in caps and gowns celebrate together outdoors.

Your Harvard 2026 Commencement Week Guide

College reunions and Alumni Day will take place the following week

A colorful hummingbird hovering by vibrant flowers.

Discoveries

Short takes on cutting-edge research